Application is filled out and
returned
(with all other necessary info. and
fees) |
| ■ |
Plans are reviewed and comments
submitted back to the engineer. |
| ■ |
Please allow us a 15-day turn around
for initial comments to plans. |
| ■ |
A letter stating "Plans now meet
Technical Standards" (staying away from
words such as approval which infers
regulatory authority). |
| ■ |
A pre-construction meeting is
scheduled. |
| ■ |
Follow-up on-site inspections. |
| ■ |
Deficiencies are made known to the
contractor for repair or maintenance.
Failure to comply will move the
situation to the next level. |
| ■ |
Letters of deficiency are mailed to
the Municipality or County for action.
|
| ■ |
Corps could invoke stop work order
or fines. |